PAC-CLAD Field Details

PAC-CLAD flashing details, step by step.

PAC-CLAD’s drawings show the finished detail. We show what it takes to get there, with photos from real standing seam jobs at every step.

Metal Formers is a certified PAC-CLAD roll former. The details here come from PAC-CLAD by Petersen and are cited in each section. The photos and steps are ours. PAC-CLAD is a trademark of Petersen Aluminum Corporation.

How to use this guide

Built for the crew on the roof

This guide follows PAC-CLAD’s Snap-Clad details for a wood deck, one detail at a time. Each section tells you what the PAC-CLAD sheet calls for, walks through the install in order, and shows it on a real roof. Tite-Loc, Tite-Loc Plus and the other PAC-CLAD panels have their own sheets, so pull the set for your panel and substrate from PAC-CLAD’s drawings page.

The details alone don’t earn the warranty

PAC-CLAD’s 20-year Weather Tightness Warranty asks for PAC-CLAD panels and flashings, PAC-CLAD HT underlayment or an approved equal, a PAC pre-approved installer, a PAC project review before bid and field inspections during the job. PAC-CLAD’s sample warranty also leaves out penetrations, curbs, skylights and gutters.

If your job needs that warranty, talk to PAC-CLAD before you bid. Read PAC-CLAD’s warranty page.

Want to see it move? Watch PAC-CLAD’s Snap-Clad install video.

Detail 01

Underlayment and layout

PAC-CLAD detail: Installation.

What PAC-CLAD calls for

  • High temperature underlayment over the whole deck. For the warranty that means PAC-CLAD HT or an approved equal.
  • Each clip gets two fasteners, with at least 5/8 in. of thread into the wood.
  • Clip and fastener spacing comes from the project loads and your local code.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Dry in the deck with high temp underlayment, lapped the way its maker calls for.
  2. Snap layout lines square to the eave so the panels don’t walk as you go.
  3. Set the first panel and check it against your line.
  4. Clip every panel leg and drive both clip fasteners.
PAC-CLAD HT underlayment rolled up from the eave over the deck
01PAC-CLAD HT underlayment rolled up from the eave over the deck
Layout lines snapped on PAC-CLAD HT before the first panel
02Layout lines snapped on PAC-CLAD HT before the first panel
First panel clipped along its leg, clip fasteners driven
03First panel clipped along its leg, clip fasteners driven

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Installation,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 02

Eave

PAC-CLAD detail: Eave Option 1 (Drip Edge) and Option 2 (Retainer Clip).

What PAC-CLAD calls for

  • Eave flashing goes on over the underlayment strip-in.
  • A 22 ga cleat on the drip edge is optional. It depends on the drip edge face height or your code.
  • Butyl tape on the flashing, then the panel end is field cut and bent into a return that hooks the eave flashing.
  • The first clip sits no more than 8 in. from the eave.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Strip in the underlayment and fasten the eave flashing.
  2. Fasten the cleat to the drip edge face if your job calls for one.
  3. Run butyl tape along the flashing where the panel will land.
  4. Notch the panel end and bend the return.
  5. Hook the return over the flashing or cleat and set the panel down into the tape.
  6. Clip the panel, first clip within 8 in. of the eave.

We fab it: Eave drip edge for Snap-Clad, 24 ga.

Eave flashing set over PAC-CLAD HT before the panels
01Eave flashing set over PAC-CLAD HT before the panels
Panel end hemmed over the drip edge at the gutter
02Panel end hemmed over the drip edge at the gutter
Finished eave
03Finished eave
Sealant bead run on the eave flashing over the PAC-CLAD HT strip in, ready for the panel hook
04Sealant bead run on the eave flashing over the PAC-CLAD HT strip in, ready for the panel hook

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Eave Option 1 (Drip Edge) and Option 2 (Retainer Clip),” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 03

Rake and gable

PAC-CLAD detail: Gable Option 3 (J-Channel), plus Options 1, 2, 4 and 5.

What PAC-CLAD calls for

  • A J-channel runs the length of the rake, with a 7/8 in. gable cleat.
  • The leg of the last panel is field formed to fit inside the J closure.
  • Underlayment is stripped in under the rake.
  • Trim fasteners are self tapping pancake heads in a staggered pattern.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Strip in the underlayment at the rake edge.
  2. Fasten the J-channel and gable cleat before the last panel goes down.
  3. Cut the last panel to width and field form its leg into the J.
  4. Hook the rake trim on the cleat and fasten it in a staggered pattern.

We fab it: Rake trim for Snap-Clad, 24 ga.

Underlayment lapped at the rake edge before panels
01Underlayment lapped at the rake edge before panels
Rake trim tied into the ridge cap
02Rake trim tied into the ridge cap
Finished gable rake and eave
03Finished gable rake and eave

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Gable Option 3 (J-Channel), plus Options 1, 2, 4 and 5,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 04

Hip and ridge

PAC-CLAD detail: Hip-Ridge, Vented Ridge Options 1 to 3, and Peak.

What PAC-CLAD calls for

  • Each panel gets a 3/4 in. turn-up at the ridge.
  • Z closures fit between the ribs, with sealant at the vertical leg and under the Z.
  • The last clip sits within 8 in. of the Z.
  • The ridge or hip cap fastens to the Z closures.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Turn up the panel ends at the ridge.
  2. Set sealant, then the Z closures between the ribs.
  3. Fasten the Z closures and tool the sealant at each leg.
  4. Set the ridge or hip cap and fasten it to the Zs.

We fab it: Ridge cap and hip cap for Snap-Clad, 24 ga, plus Z-bar.

Hip cap lap set in sealant
01Hip cap lap set in sealant
Ridge cap tied into two hip caps
02Ridge cap tied into two hip caps

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Hip-Ridge, Vented Ridge Options 1 to 3, and Peak,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 05

Z closures up close

PAC-CLAD detail: Z-Closure Detail.

What PAC-CLAD calls for

  • Cut each Z to fit tight between the ribs.
  • Sealant goes under the Z and up the back of each leg.
  • Z fasteners run no more than 4 in. apart.
  • On low slopes (under 4:12) the detail may call for bread-panning. Check the sheet for your slope.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Measure between ribs and cut the Z to fit.
  2. Lay a bead under the Z and up both legs.
  3. Set the Z and fasten at 4 in. or closer.
  4. Tool the sealant at each leg.

We fab it: Z-bar for Snap-Clad, 24 ga.

Z closures fastened on both sides of a hip, seam ends sealed, before the cap
01Z closures fastened on both sides of a hip, seam ends sealed, before the cap

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Z-Closure Detail,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 06

Valley

PAC-CLAD detail: Valley Option 1 (With Diverter), plus Options 2 and 3.

What PAC-CLAD calls for

  • Valley flashing over a stripped-in underlayment.
  • A 1 1/2 in. hem with 1/2 in. of thermal clearance.
  • Valley retainer clips set in sealant.
  • Keep the minimum 6 in. clearance shown on the detail.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Strip in the valley underlayment.
  2. Lay and fasten the valley flashing.
  3. Set the retainer clips in sealant.
  4. Cut each panel to the valley line, hem it and hook it on the clip.

We fab it: Valley for Snap-Clad, 24 ga.

Valley underlayment stripped in over PAC-CLAD HT
01Valley underlayment stripped in over PAC-CLAD HT

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Valley Option 1 (With Diverter), plus Options 2 and 3,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 07

Headwall

PAC-CLAD detail: Headwall Option 3 (Counterflashing), plus reglet options.

What PAC-CLAD calls for

  • Panels get a 3/4 in. turn-up at the wall.
  • A Z closure with sealant at the leg and under the Z.
  • Headwall flashing over the Z, then counterflashing.
  • Tube sealant at the counterflashing, 6 in. minimum where the detail shows it.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Run underlayment up the wall before any metal.
  2. Turn up the panels and set the Z closures in sealant.
  3. Fasten the headwall flashing to the Zs.
  4. Install the counterflashing or reglet and seal it.

We fab it: Headwall flashing and counter flashing, 24 ga.

Headwall flashing staged above the clips, panels next
01Headwall flashing staged above the clips, panels next
Finished headwall flashing at a brick wall
02Finished headwall flashing at a brick wall

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Headwall Option 3 (Counterflashing), plus reglet options,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 08

Sidewall

PAC-CLAD detail: Rakewall Option 3 (Counterflashing, Floating), plus Options 1, 2 and 4.

What PAC-CLAD calls for

  • Rakewall flashing runs at least 4 in. up the wall, with a J closure.
  • The panel leg is field formed into the J.
  • 4 in. counterflashing over the top, with tube sealant.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Run underlayment up the wall.
  2. Fasten the sidewall cleat or J closure.
  3. Form the panel leg into the J.
  4. Set the sidewall flashing and counterflash it.

We fab it: Side wall flashing, 24 ga.

Underlayment run up a parapet sidewall before the flashing
01Underlayment run up a parapet sidewall before the flashing
Sidewall cleats fastened along brick before the flashing
02Sidewall cleats fastened along brick before the flashing

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Rakewall Option 3 (Counterflashing, Floating), plus Options 1, 2 and 4,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 09

Chimney

PAC-CLAD detail: Built from the Headwall and Rakewall details, plus a cricket.

What PAC-CLAD calls for

  • The sides of the chimney follow the rakewall detail.
  • The downslope face is a headwall: panels turn up and get a Z closure and counterflashing.
  • The upslope side gets a cricket so water runs around the chimney.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Run underlayment up all four sides.
  2. Build and flash the cricket.
  3. Flash the sides and the downslope face.
  4. Counterflash all the way around.

We fab it: Cricket and chimney flashings fabricated to your measurements.

Cricket formed on the upslope side of a chimney
01Cricket formed on the upslope side of a chimney
Counterflashing tucked into a mortar joint on a stone chimney, lapped over the base flashing
02Counterflashing tucked into a mortar joint on a stone chimney, lapped over the base flashing

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Built from the Headwall and Rakewall details, plus a cricket,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 10

Pipe penetrations

PAC-CLAD detail: Pipe Penetration Option 1 (Fixed), plus Options 2 and 3.

What PAC-CLAD calls for

  • The boot sits in the flat of the panel, never across a seam.
  • A square base is set diamond-wise so it sheds water.
  • The hole is cut 1 in. smaller than the pipe, back cut and turned up.
  • NP1 sealant, tooled. Gasketed fasteners go into the panel, not the deck. Stainless fasteners through aluminum.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Lay out the boot in the panel flat.
  2. Cut the hole small, back cut it and turn the edge up.
  3. Seal and seat the boot.
  4. Fasten through the panel with gasketed fasteners.
Pipe boot on the panel flat with its clamping ring
01Pipe boot on the panel flat with its clamping ring
Larger boot sealed and fastened to the panel flat
02Larger boot sealed and fastened to the panel flat

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Pipe Penetration Option 1 (Fixed), plus Options 2 and 3,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 11

Curbs and skylights

PAC-CLAD detail: Curb.

What PAC-CLAD calls for

  • Curbs get an upslope diverter so water runs around them.
  • PAC-CLAD’s sample warranty leaves curbs and skylights out.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Frame and set the curb.
  2. Flash the downslope side, then the sides.
  3. Add the upslope diverter.
  4. Seal and counterflash to the curb.
Curb pan fit over the panel and seamed by hand
01Curb pan fit over the panel and seamed by hand
Curb flashing over the panels with the upslope diverter formed
02Curb flashing over the panels with the upslope diverter formed

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Curb,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.

Detail 12

Panel ends, slope changes and transitions

PAC-CLAD detail: Panel End, Slope Change Options 1 and 2, Transition to and from Membrane.

What PAC-CLAD calls for

  • Each of these has its own sheet. Pull the one for your condition before you cut anything.
PAC-CLAD drawingWe’ll show PAC-CLAD’s drawing for this detail here once Petersen okays it. For now, open it on PAC-CLAD’s Snap-Clad page under PDF Details.

Step by step on the roof

  1. Find the sheet for your exact condition.
  2. Match the closure and sealant it calls for.
  3. Flash the change before the next run of panels.

We fab it: Transition flashing, 24 ga.

Flashing turned up where a gable sits on the roof, set over PAC-CLAD HT before the trim closes it in
01Flashing turned up where a gable sits on the roof, set over PAC-CLAD HT before the trim closes it in
Panel ends at a slope change, ready for closures and the cover flashing
02Panel ends at a slope change, ready for closures and the cover flashing
Cover flashing across the panel ends at the slope change, fastened along its top edge
03Cover flashing across the panel ends at the slope change, fastened along its top edge

Source: PAC-CLAD by Petersen Aluminum Corporation, Snap-Clad Wood Substrate Details, “Panel End, Slope Change Options 1 and 2, Transition to and from Membrane,” effective 01-03-2023. pac-clad.com. PAC-CLAD’s detail and your approved shop drawings govern. Photos are from real jobs and show one way to meet the detail.